Tag Archives: Nimal

R15: The Writing Week

[Work done from 12th January to 25th January 2009] Ramanan: During first week of this two week period I was working with the integration of JCOP 41 Java Card and eID Browser Extension together with the eID Desktop Application. Before … Continue reading

Leave a Comment

Filed under Reports

R14: Starting to Write

[Work done from 29th December 2008 to 11th January 2009] During this two weeks period I was involved in the following activities in our project: Completing the Card Creation Application: I was not able to finish this in time as … Continue reading

Leave a Comment

Filed under Reports

R13: A Presentation Week

[Work done from 15th December to 28th December 2008] During this period we were in the final stage development of most of the modules and also we participated in a competition out of the university. We applied for the World … Continue reading

Leave a Comment

Filed under Reports

R12: Completing eID Offline App

[Work done from 1st December to 14th December 2008] Project Management During this time we decided to go with a tightly planned schedule with individual deadlines as to make sure that we work according to plans and finish in time. … Continue reading

Leave a Comment

Filed under Reports

R11: Demonstration Time

[Work done from 17th November to 30th November 2008] I mainly worked on two components of the project during this stage. eID Information Card This is an XML based file where the digital information of the card holder will be … Continue reading

Leave a Comment

Filed under Reports

R10: Offline Application and Deadlines

[Work done from 3rd November to 16th November 2008] We started working more on the project as we had set some of our own deadlines after our switch to the new architecture. I’ve been working on the Read Only USB … Continue reading

Leave a Comment

Filed under Reports

R9: A new direction

[Work done from 20th October to 2nd November 2008] During this period we had couple of meetings with our project supervisor Dr. Chandana Gamage, which lead us to a redesign of our architecture. We found that there were some flaws … Continue reading

Leave a Comment

Filed under Reports

R8: Vacation during Project

Its Vacation during Project, not Project during Vacation I started back working on the project couple of days after the exam. The first thing we had to do was to finalize the architecture in the online authentication and web services … Continue reading

Leave a Comment

Filed under Reports

R7: Draft paper and Design document

[Work done from 18th August to 31st August 2008] During the last two weeks we were engaged in the following tasks: Completing the draft paper of the research on ‘Privacy Enhanced Data Management in eID Systems’ Preparing the design document … Continue reading

Leave a Comment

Filed under Reports

R6: Problems and Redesign

[Work done from 4th August to 17th August 2008] During this period of two we involved in developing a prototype that could be used to demonstrate our system. But we were unable to complete that due to some misunderstandings and … Continue reading

Leave a Comment

Filed under Reports