Archive for August 2008

Group Discussion – 28-08-2008

We had a group discussion today afternoon. This is the summery of outcomes. Discussion Topics: Information is contained in the eID card Problems identified Lost cards Forget passkeys What next? eID will be based on Public Key Infrastructure (PKI) and certificates. In addition to any technical data, the card will contain the Certification Authority certificates [...]

R6: Initial Prototyping

[Work done from 4th August to 17th August 2008] During the last fortnight we were focusing in developing a prototype for our eID system. And also we had a meeting with our project supervisor on August 15. This meeting was mainly focused on how we are progressing and what we need to do soon. He [...]

R6: Initial Architecture

[Work done from 4th August to 17th August 2008] At the start of this two week period we were mainly concerned about implementing our early developed system architecture with the identified requirements. We’re doing research and we tested the WSO2 identity solution which is a kind of authentication providing system for enterprises. It uses the [...]

R6: Problems and Redesign

[Work done from 4th August to 17th August 2008] During this period of two we involved in developing a prototype that could be used to demonstrate our system. But we were unable to complete that due to some misunderstandings and problems. We found most of these problems after the meeting we had with our project [...]

R6: Into Web Services

[Work done from 4th August to 17th August 2008] On 15th of August we had a meeting with Dr.Chandana Gamage and we discussed lots of things regards the project. In that meeting we mainly concerned about the Privacy and Unlinkability of the eID. Because of less Privacy and Unlinkability maybe case failure of the eID [...]

Meeting with Project Supervisor (15-08-2008)

We had a meeting with our project supervisor Dr. Chandana Gamage today from 1.15pm to 3.45pm. Main Points Privacy – The privacy of the holder will be the key feature in our eID when comparing to other similar implementations. Thus we must ensure privacy protection is there in the very system level. Unlinkability – This [...]

R5: Presentation and Feedback

[Work done from 21st July to 3rd August 2008] On 24th of July we had our first formal presentation, and the day before that day we completed the presentation and did a demonstration to our project supervisor Dr.Chandana Gamage. He gave us his feedbacks and they were really helpful to make up our presentation in [...]

R5: Creating the Project Website

[Work done from 21st July to 3rd August 2008] We had the first formal presentation on the 24th of July which was to on the work done up to end of June 2008. We prepared for the presentation as the group and did a demonstration of that on the 22nd to our project supervisor Dr. [...]

R5: WSO2 Identity Solution and eID

[Work done from 21st July to 3rd August 2008] 24th of July we did the 1st Formal presentation. So within first one week time period we were busy with preparing a short presentation. So we discussed about the presentation, with project supervisor Dr.Chandana Gamage. We had two meetings with him during that period. Those meetings [...]

R5: Java Applets and USB Access

[Work done from 21st July to 3rd August 2008] We had very interesting and effective progress in our project during the last fortnight. First half of the week we mainly focus on the demonstration about our project progress to the Subject coordinator. We met our supervisor Dr.Chandana Gamage two times for that presentation. Meeting with [...]